BUG 8038 Case Scheduler add a way to schedule tasks more often than... SOLVED
- According to the specifications. - Was added the option "Every" that run the task each X hours.
This commit is contained in:
@@ -63,17 +63,19 @@ try {
|
||||
$sOption = $_POST['form']['SCH_OPTION'];
|
||||
$aData['SCH_OPTION'] = $sOption;
|
||||
|
||||
if ($_POST['form']['SCH_START_DATE']!=''){
|
||||
$sDateTmp = $_POST['form']['SCH_START_DATE'];
|
||||
} else {
|
||||
$sDateTmp = date('Y-m-d');
|
||||
}
|
||||
$sTimeTmp = $_POST['form']['SCH_START_TIME'];
|
||||
$aData['SCH_START_TIME'] = date('Y-m-d', strtotime($sDateTmp)) . ' ' . date('H:i:s', strtotime($sTimeTmp));
|
||||
$aData['SCH_START_DATE'] = date('Y-m-d', strtotime($sDateTmp)) . ' ' . date('H:i:s', strtotime($sTimeTmp));
|
||||
|
||||
$nActualTime = $_POST['form']['SCH_START_TIME']; // time();
|
||||
// $nActualDate = date("Y-m-d H:i:s", $nActualTime);
|
||||
|
||||
if ($_POST['form']['SCH_START_DATE']!=''){
|
||||
$sDateTmp = $_POST['form']['SCH_START_DATE'];
|
||||
} else {
|
||||
$sDateTmp = date('Y-m-d');
|
||||
}
|
||||
$sTimeTmp = $_POST['form']['SCH_START_TIME'];
|
||||
$aData['SCH_START_TIME'] = date('Y-m-d', strtotime($sDateTmp)) . ' ' . date('H:i:s', strtotime($sTimeTmp));
|
||||
$aData['SCH_START_DATE'] = date('Y-m-d', strtotime($sDateTmp)) . ' ' . date('H:i:s', strtotime($sTimeTmp));
|
||||
|
||||
$nActualTime = $_POST['form']['SCH_START_TIME']; // time();
|
||||
// $nActualDate = date("Y-m-d H:i:s", $nActualTime);
|
||||
|
||||
$sValue = '';
|
||||
$sDaysPerformTask = '';
|
||||
@@ -161,7 +163,8 @@ try {
|
||||
|
||||
|
||||
}
|
||||
if(($sOption!='1') && ($sOption!='4')) {
|
||||
echo "<br>sOption: ".$sOption;
|
||||
if(($sOption!='1') && ($sOption!='4') && ($sOption!='5') ) {
|
||||
if ($sStartDay==''){
|
||||
$sStartDay = date('Y-m-d');
|
||||
}
|
||||
@@ -190,8 +193,17 @@ try {
|
||||
$aData['SCH_END_DATE'] = $aData['SCH_START_TIME'];
|
||||
}
|
||||
$aData['SCH_TIME_NEXT_RUN'] = $aData['SCH_START_TIME'];
|
||||
if ($sOption == 5) {
|
||||
$aData['SCH_START_TIME'] = time();
|
||||
$aData['SCH_START_DATE'] = $aData['SCH_START_TIME'];
|
||||
$nextRun = $_POST['form']['SCH_REPEAT_EVERY']*60*60;
|
||||
$aData['SCH_REPEAT_EVERY'] = $_POST['form']['SCH_REPEAT_EVERY'];
|
||||
$date = $aData['SCH_START_TIME'];
|
||||
$date += $nextRun;
|
||||
$date = date("Y-m-d H:i", $date );
|
||||
$aData['SCH_TIME_NEXT_RUN'] = $date;
|
||||
}
|
||||
}
|
||||
|
||||
if(trim($_POST['form']['SCH_END_DATE'])!=''){
|
||||
$aData['SCH_END_DATE'] = $_POST['form']['SCH_END_DATE'];
|
||||
}
|
||||
|
||||
@@ -46,7 +46,6 @@ try {
|
||||
if (empty($_POST)) {
|
||||
die('The information sended is empty!');
|
||||
}
|
||||
|
||||
$aData['SCH_UID'] = $_POST['form']['SCH_UID'];
|
||||
$aData['SCH_NAME'] = $_POST['form']['SCH_NAME'];
|
||||
$aData['PRO_UID'] = $_POST['form']['PRO_UID'];
|
||||
@@ -162,7 +161,7 @@ try {
|
||||
$aData['SCH_END_DATE'] = $_POST['form']['SCH_END_DATE'];
|
||||
}
|
||||
// if the start date has changed then recalculate the next run time
|
||||
if ($_POST['form']['SCH_START_DATE']==$_POST['form']['PREV_SCH_START_DATE']){
|
||||
if ($_POST['form']['SCH_START_DATE']==$_POST['form']['PREV_SCH_START_DATE']) {
|
||||
$recalculateDate = false;
|
||||
} else {
|
||||
$recalculateDate = true;
|
||||
@@ -177,7 +176,7 @@ try {
|
||||
// var_dump($recalculateTime);
|
||||
// die();
|
||||
$nActualTime = $_POST['form']['SCH_START_TIME'];
|
||||
if(($sOption!='1') && ($sOption!='4')) {
|
||||
if(($sOption!='1') && ($sOption!='4') && ($sOption!='5')) {
|
||||
if ($sStartDay==''){
|
||||
$sStartDay = date('Y-m-d');
|
||||
}
|
||||
@@ -230,6 +229,18 @@ try {
|
||||
// var_dump($recalculateTime);
|
||||
// var_dump($aData['SCH_TIME_NEXT_RUN']);
|
||||
// die;
|
||||
if ($sOption=='5') {
|
||||
$date = $oCaseScheduler->getSchLastRunTime();
|
||||
if ($date == null) {
|
||||
$date = $oCaseScheduler->getSchStartTime();
|
||||
}
|
||||
$date = strtotime($date);
|
||||
$nextRun = $_POST['form']['SCH_REPEAT_EVERY']*60*60;
|
||||
$aData['SCH_REPEAT_EVERY'] = $_POST['form']['SCH_REPEAT_EVERY'];
|
||||
$date += $nextRun;
|
||||
$date = date("Y-m-d H:i", $date );
|
||||
$aData['SCH_TIME_NEXT_RUN'] = $date;
|
||||
}
|
||||
}
|
||||
|
||||
if(!empty($_POST['form']['SCH_REPEAT_TASK_CHK'])){
|
||||
|
||||
Reference in New Issue